What are the rules for placing concrete in cold weather on Louisiana DOT projects?

Do not place concrete if internal temp <45°F or subgrade/frozen forms <32°F. Discontinue PC mixes at ≤35°F air temp or NOAA forecast <32°F in 24h; resume only when air temp ≥32°F for ≥24h with NOAA high >35°F. For binary mixes, discontinue at ≤40°F or NOAA forecast <35°F in 36h; resume at ≥40°F for ≥36h with NOAA high >45°F. For ternary mixes, discontinue at ≤45°F or NOAA forecast <40°F in 48h; resume at ≥45°F for ≥48h with NOAA high >50°F. Written authorization required for operations outside these limits.

Every answer carries its source — tap a citation to read the official document.

This answer came from Verika — an expert in your pocket. Ask anything, out loud or typed; answers come from your region’s regulations and your team’s own knowledge, cited to the source. If it isn’t in the sources, Verika says so.

Verika provides information with citations to help you find and understand the rules that apply to your work. It is not a substitute for professional engineering or legal judgment. Answer generated 2026-08-28; always confirm against the cited source for your project.

More Louisiana answers