For Arizona DOT projects, concrete placed at elevations 3,000 feet or above must have an air content of 4–7% (if freeze-thaw concern exists) or 5–8% (if freeze-thaw concern exists and concrete is pumped). Below 3,000 feet, air entrainment is optional, with a max of 7% if used. [2,6]