What are the rules for placing concrete in cold weather on Arkansas DOT projects?
Concrete placement in cold weather on Arkansas DOT projects requires: (1) No placement if air temp < 36°F (2°C) unless heating ingredients and enclosing concrete is approved [4,6]. (2) Minimum concrete placement temp: 50°F (10°C) [2,6]. (3) Protection methods: insulated forms, blankets, or heating to maintain adjacent concrete temp ≥50°F (10°C) for 7 days (or prevent freezing for non-bridge work) [2,6]. (4) Class B concrete: forms must stay 4+ days if temps ≤40°F (4°C), with insulated blankets on exposed surfaces [2]. (5) Frozen aggregates prohibited [2]. (6) Heating methods: dry heat/steam only (no direct flame); water ≤180°F (82°C) [2]. (7) Frozen/damaged concrete must be removed/replaced [2].
Every answer carries its source — tap a citation to read the official document.
This answer came from Verika — an expert in your pocket. Ask anything, out loud or typed; answers come from your region’s regulations and your team’s own knowledge, cited to the source. If it isn’t in the sources, Verika says so.
Verika provides information with citations to help you find and understand the rules that apply to your work. It is not a substitute for professional engineering or legal judgment. Answer generated 2026-08-28; always confirm against the cited source for your project.