Massachusetts · answered by Verika · verified against sources
What air content is required for concrete on Massachusetts DOT projects?
Air content must meet the target ±1.5% as tested by AASHTO T 309 for fresh concrete on MassDOT projects.
Massachusetts DOT Standard Specifications, pp. 268–269Massachusetts DOT Standard Specifications, pp. 546–547
Every answer carries its source — tap a citation to read the official document.
This answer came from Verika — an expert in your pocket. Ask anything, out loud or typed; answers come from your region’s regulations and your team’s own knowledge, cited to the source. If it isn’t in the sources, Verika says so.
Verika provides information with citations to help you find and understand the rules that apply to your work. It is not a substitute for professional engineering or legal judgment. Answer generated 2026-08-28; always confirm against the cited source for your project.